To plan a Venetian plaster order around a UAE fit out programme, place the material order once the colour is approved and the walls are measured, early enough that the tubs are on site and stored before the first coat is due. Zavoré tints every order in the UK to the approved sample, sends it to the Emirates on a tracked service, and quotes delivery individually for each consignment.
The materials themselves are listed in the Zavoré shop, and our page on Venetian plaster supply for the UAE sets out how international orders run. Our overview of Venetian plastering in the UAE explains what happens when our own artisans install the finish instead.
Decorative plaster is one of the last wet trades on a fit out, but it should be one of the first to be decided. The colour and finish affect lighting, joinery and stone choices, and the material is made and tinted in the UK. A sound programme treats the plaster as two separate items, the design decision early on and the site work near the end.
On a typical villa or hotel fit out in Dubai or Abu Dhabi, the order of events looks something like this.
Place it once the board is approved and the quantities are firm, and before the walls are ready, not after. The material needs time to be tinted, packed and carried, and then to clear customs. Delivery is quoted individually for each order, so ask for the quote at the quantities stage and build transit and clearance into the programme as a defined step. If the programme is tight, a phased order is often wiser than one large consignment that arrives before there is anywhere to keep it.
Venetian plaster rewards a quiet site. Before the first coat, the walls should be flat, dry and primed, and other work that throws dust or water around should be done. In practice that usually means the following are complete or protected.
Joinery and flooring are often fitted after the plaster, with good protection in place, though every project is different. Discuss the order with your applicators early.
Most delays on a decorative finish come from an unclear approval. A board approved by email from the designer, the client and the contractor removes any doubt. If the scheme has several colours, list each with its room code and attach the approval to the drawing. We label the tubs to match, so the store on site is easy to manage. For a Dubai project, our page on Venetian plastering in Dubai shows how finishes are typically used by room.
Once the order is confirmed, the plaster leaves the UK on a tracked service. The delivery figure depends on weight, the number of tubs and the address, and we confirm it by email before dispatch. Import duty or tax is set by the UAE and paid by the buyer, so your clearing agent should be ready. Most towers and communities have management rules on working hours and deliveries, so check with yours and book the delivery slot in advance.
On arrival, move the tubs out of the sun straight away. Keep them sealed, indoors and ideally air conditioned, and never in a vehicle or on a roof. Leave any spare from the tinted batch labelled for future repairs and handover.
If your team has skilled applicators, supply only keeps you in control of the site programme. If not, our own artisans install in every emirate. Our Venetian plaster installation page describes the sequence of survey, sample approval, protection, preparation, primer, coats with drying between them, polishing and waxing. Our page on Venetian plastering in Abu Dhabi covers the capital.
Yes. Many fit outs order by floor or by zone. Each phase is tinted to the same approved board and labelled, and each consignment is sent tracked with delivery quoted individually. Keep the board on site so every phase can be compared against it.
Tell us straight away with the revised areas. If more material is needed, we tint a further order to the same approved board. Adding a sensible margin to the first order reduces the chance of a short top up later.
It can, provided it is stored properly. Keep tubs sealed, shaded and indoors, ideally in an air conditioned room. Avoid containers in the sun, vehicles and roof areas, and keep the labels facing out so rooms are easy to identify.
The buyer. Import duty or tax is set by the UAE and paid by the buyer, so most fit out firms use their usual clearing agent. Build the cost and the clearance step into the budget and the programme from the start.
Planning a fit out in Dubai, Abu Dhabi or another emirate? Send the drawings, the approved finish and colour, rough measurements and the site address to sales@zavore.co.uk, or ring +44 7592 929191, Monday to Saturday from 9am to 6pm UK time.
Why UAE designers and homeowners order the printed Colour Booklet or Venezia Stucco Colour Catalogue before sample boards, and how printe...
CommercialWhere polished plaster works in Dubai gyms and fitness clubs, how scuff zones and changing areas are handled, and how Zavoré plans around...
Abu DhabiA plain guide to import duty and tax on Venetian plaster sent from the UK to the UAE, who pays it, what paperwork to expect and who to ask.
Abu DhabiHow Zavoré plans marmorino installation for Ramhan Island and Nurai Island villas, from soft matt lime finishes to fit out timing and isl...
Abu DhabiHow Zavoré tints Venetian plaster for UAE orders to one of 48 house colours or any NCS reference, and why the sample board check matters.
Abu DhabiHow to buy Travertino plaster in the UAE for stone look walls, from choosing colour and pitting on a sample board to quantities, waxes an...
Providing luxury finishes for the most prestigious addresses in the world
Venetian plaster, limewash, microcement, tadelakt, metallics, sculptural plaster and gold leaf, supplied and installed by our own team, with Venetian plaster taught at our Birmingham studio.
One list, run by the people who make the material. No noise, and nothing we would not want to read ourselves.
We email as the house has something worth saying, never daily. Unsubscribe from any email, or reply STOP to any text. We never pass your details to anyone.