Tracked delivery across the UK and worldwide·Same day and 24 hour delivery available·Venetian plaster tinted to your exact colour·Damaged in transit? We’ll replace it within 24 hours or on the same day·Speak to a specialist · 07592 929191·Residential and commercial projects installed by our own team·Trade accounts · 10% and rewards·Training courses at our studio·Showroom · visit by appointment·Tracked delivery across the UK and worldwide·Same day and 24 hour delivery available·Venetian plaster tinted to your exact colour·Damaged in transit? We’ll replace it within 24 hours or on the same day·Speak to a specialist · 07592 929191·Residential and commercial projects installed by our own team·Trade accounts · 10% and rewards·Training courses at our studio·Showroom · visit by appointment·
Home/The Journal/How Venetian Plaster Sample Approval Works on UAE Projects
20 November 2026

How Venetian Plaster Sample Approval Works on UAE Projects

Practice panels of Venetian plaster laid out for comparison, showing how sample approval works on UAE projects

Venetian plaster sample approval on UAE projects works like this with Zavoré. A sample board is made in the proposed colour and finish, the owner, designer and contractor view it in the actual room at different times of day, one named person signs it off in writing, and that approved board then stays on site as the reference every wall is judged against until handover.

Sample approval sits at the heart of our Venetian plaster installation process, and it applies just as much when you buy material alone through our Venetian plaster supplier page for the UAE. For how we plan projects across the Emirates, see Venetian plastering in the UAE.

  • One board per finish and colour, made from the real material.
  • Viewed in the room in morning, afternoon and evening light.
  • Approved in writing by the person with authority to decide.
  • Kept on site, protected, as the reference for every wall.
  • Any change after sign off means a new board and a new approval.

Why sample approval matters on UAE projects

Venetian plaster is handmade, so no screen image or printed swatch can show exactly how it will look on your wall. On UAE projects there are often several people involved, such as a villa owner, an interior designer, a main contractor and sometimes a developer or hotel brand team. Without one agreed board, each person can carry a slightly different picture in their head. The approval step gives everyone the same physical reference and avoids disputes once the walls are finished.

Who approves a Venetian plaster sample in the UAE

Agree at the start who has the final word. On a private villa it is usually the owner, guided by the designer. On a commercial fit out it may be the client representative or the design lead. The contractor needs to know who that person is, and so do we.

  1. The designer proposes the finish, colour and sheen.
  2. The owner or client views the board in the room and decides.
  3. The contractor confirms the board is practical for the walls and the programme.
  4. One named person signs and dates the approval.

How to view a sample board in a UAE room

Light in the Emirates can be strong and bright through big windows by day, then warm and low under lamps at night. A colour that looks pale at noon may look deeper in the evening. So hold the board against the wall it is meant for, upright, and look again in the morning, in the afternoon and after dark with the room lights on. Check it next to the floor, the joinery and the fabrics. In a majlis or a formal dining room, judge it under the chandelier or the lighting you will actually use.

  • Do not judge a board lying flat on a table.
  • Do not judge it outdoors or in a different room.
  • Do compare two or three boards side by side if you are unsure.

What written approval should record on a UAE project

A short email is enough, but it should be clear. Name the product and finish, the colour reference, the rooms or walls it covers, the sheen and any wax or sealer shown on the board, the date, and the name of the person approving it. Attach a photo of the board in the room. If there are several boards, label each one and match the labels to the approval.

Keeping the approved board on site

The approved board becomes the project's reference. Keep it on site, wrapped and stored somewhere cool and shaded, and bring it out when each wall is finished so the owner, designer and contractor can compare like with like. At handover, the client can keep it for future repairs or extensions.

What happens if someone wants a change after sign off

Changes happen. If the colour, sheen or finish changes after approval, we make a new board and the approval step starts again. That is not a delay for its own sake. It protects the walls already finished and keeps everyone working to the same reference.

Projects in Dubai follow the same approach, which you can read about on Venetian plastering in Dubai, and the capital is covered on Venetian plastering in Abu Dhabi.

Questions about Venetian plaster sample approval in the UAE

How many sample boards do I need for a UAE villa?

Usually one board per finish and colour. A villa with a polished plaster majlis, marmorino corridors and a limewash bedroom would need three. If you are torn between shades, order two or three boards for the same room and compare them side by side.

Can a designer approve the sample on behalf of the owner?

Yes, if the owner agrees that the designer has that authority. Put it in writing at the start of the project, so everyone knows whose signature on the board counts.

Do material only orders to the UAE need sample approval too?

Yes. We tint material orders to an approved board, just as we do for installations. It gives your applicator and your client the same reference and makes sure the tubs that arrive match what was agreed.

What if the finished wall looks different from the board?

Bring the approved board to the wall and compare them in the same light. Hand finishes vary a little by nature, but the colour and sheen should read the same. That is why the board stays on site throughout.

To start the approval step, order a Venetian plaster sample board, or call +44 7592 929191, Monday to Saturday, 9am to 6pm UK time. You can also email sales@zavore.co.uk with photos of the room, rough measurements and the project address.

Back to the Journal

Providing luxury finishes for the most prestigious addresses in the world

Venetian plaster, limewash, microcement, tadelakt, metallics, sculptural plaster and gold leaf, supplied and installed by our own team, with Venetian plaster taught at our Birmingham studio.

PayPal
© 2026 Zavoré Ltd · Est. 2021 · Made to order in Birmingham
For The Trade Three ways to earn with us
Trade accountTen percent off every material in the shop, and a specialist on the phone. Partners & affiliatesGet listed where customers find you, or sell our materials and earn on every order. The Rewards RoomEvery order earns. Samples, tools and an apron, on the house.
Free to join · we reply within 24 hours
DE